Creating a Microsoft Project Plan with a 24 Hour CalendarApplies to: Microsoft Project 2013 Microsoft Project 2010 Microsoft Project 2007 (End of Document) From the menu, select Project Project Information. Press the Calendar drop-down list and select the 24 Hours calendar and then press the OKbutton.11767 Katy Freeway, Suite 1010 Houston, TX 77079 713.589.2655 www.ExcelSolutionsTeam.com

From the menu, select View Timescale Drop-Down list Timescale. Select the Non-Working time tab, and press the Calendar drop-down list and select the 24Hours calendar. Next press the OK button.11767 Katy Freeway, Suite 1010 Houston, TX 77079 713.589.2655 www.ExcelSolutionsTeam.com

Select the Non-Working time tab, and press the Calendar drop-down list and select the 24Hours calendar. Next press the OK button. From the menu, select File Options Schedule. Make the following changes: Change the Hours per week value to 168. Change the Hours per day value to 24. Change the Default start time value and the Default end time value to 12:00 AM.11767 Katy Freeway, Suite 1010 Houston, TX 77079 713.589.2655 www.ExcelSolutionsTeam.com

Change the Days per month to 30. Press the OK button, when the above changes have been completed. Notes: If you have resources in the Resource Sheet view of your project, you should alsochange their Base Calendar value to the 24 Hours calendar. If you have entered tasks with durations prior to making the changes above,you may need to re-enter the durations to their correct values for each task.Steps for 2007 Users From the menu, select Project Project Information. Press the Calendar drop-down list and select the 24 Hours calendar and then pressthe OK button. From the menu, select Format Timescale. Select the Non-Working time tab, and press the Calendar drop-down list andselect the 24 Hours calendar. Next press the OK button. From the menu, select Tools Options Calendar.Make the following changes: Change the Hours per week value to 168. Change the Hours per day value to 24. Change the Default start time value and the Default end time value to 12:00 AM. Change the Days per month to 30. Press the OK button, when the above changes have been completed. Notes: If you have resources in the Resource Sheet view of your project, you should alsochange their Base Calendar value to the 24 Hours calendar.11767 Katy Freeway, Suite 1010 Houston, TX 77079 713.589.2655 www.ExcelSolutionsTeam.com

If you have entered tasks with durations prior to making the changes above,you will need to re-enter the durations to their correct values for each task.11767 Katy Freeway, Suite 1010 Houston, TX 77079 713.589.2655 www.ExcelSolutionsTeam.com